This will be a weekly thing just so ya'll know. When you put in the hours I do you become pretty tired. So here is last week in a nut shell :)

Monday- In the morning a delivery truck dropped of 36 inch concrete storm sewer pipe! Extremely huge by the way. The pipe crew had to lower sewer laterals all week and since the pipes have asbestos in it they had to be extra careful. It is taking time. For the grading crew they continued to excavate the road to get ready for curb and gutter to be poured by the end of the week. The contractor pouring the retaining wall showed up to start working on the wall. After they pour the footing it takes a week to cure and since I am writing this 9 days later, they just showed up today to pour the stem so one more week of curing. One of the mixing trucks hit a cable line but luckily it didn't break :/

Tuesday- On this day nothing changed from the previous day. One thing that was different is that we had to perform some stabilization on the grade. That consisted of digging down 1 foot and filling the hole in with 4 inch minus or shell. This helps with the overall grade of the road so that in the future it won't fail. I had to measure out the areas of the digouts for payment so I have to be as accurate as possible.

Wednesday- I get to the site on this morning to find out the grader has a flat tire. Having gotten to know the crew over the last month I have learned a lot. Donny the foreman for the grading crew takes pride in what he does. His equipment is like a kids toys in a sandbox. Don't mess with him! The tire got fixed and he was up and running in no time. My mentor David had decided to go on vacation for the rest of the week. Another inspector showed up on the site to get familiar with the project. Good thing for him and for me the next two days would not be that exciting, haha

The next two days- I found myself for the first time looking for something to do. The crews where basically slowing down for the week. Grading was almost done and they had curb and gutter set for Monday. The sewer laterals finished up Friday and on Thursday they found out they have to relocate some water services because they are in the way of the 36 inch pipe. What is new! So water lines are on the agenda for Monday and the pipe crew.

One cool thing about this week was I got to know another inspector. The funny thing is this inspector has the same name as a friend of mines in engineering at OSU. Jake Pritchard is his name. One the the funniest things. The only thing I feel bad for the guy is that he lives in Roseburg! I live in Medford. If you are not familiar with the distance between the two cities, that is exit 30 to exit 124! Almost 200 miles a day! Just to support his wife and 11 year old daughter! I have such great respect for that guy. If I ever have to do that to support my family I will, but man it must be tough. 3 years and counting he has done this.

I got paid at the end of that week and I was pretty happy with the outcome. Not only is the internship an experience but it pays good that is for sure. Not complaining one bit :)